Unavailability of contracted storage capacity due to planned or unplanned maintenance

Maintenance planned for the year 2019

StartEndImpact on max. technical storage capacity
13.05.2019 07:0016.05.2019 16:00100% reduction of withdrawal capacity
16.05.2019 16:0024.05.2019 12:0050% reduction of injection capacity
50% reduction of withdrawal capacity
24.05.2019 12:0031.05.2019 12:0025% reduction of injection capacity
25% reduction of withdrawal capacity
31.05.2019 12:0019.07.2019 12:0025% reduction of withdrawal capacity
14.10.2019 07:0028.10.2019 07:0025% reduction of injection capacity
25% reduction of withdrawal capacity
28.10.2019 07:0031.10.2019 16:0050% reduction of injection capacity
50% reduction of withdrawal capacity
31.10.2019 16:0008.11.2019 12:0050% reduction of injection capacity
50% reduction of withdrawal capacity